U.S. Chemical Safety and Hazard Investigation Board, Report No. 2010-10-I-OS, Volume 2, 5 June 2014.

Overview

The CSB's technical analysis of the blowout preventer. It found that the drill pipe buckled because of "effective compression" from pressure differences, not only the blowout flow; that the blue control pod was miswired and its battery drained, and a valve in the yellow pod was miswired; and that the deadman system most likely functioned but the buckled pipe stopped the rams from sealing. It argues that the BOP was not managed as safety-critical equipment.

Key pages

Printed page numbers, from the report's own table of contents.

  • Synopsis and key findings: pp. 13–16.
  • How the BOP was functioned: p. 23.
  • The BOP: failure of a barrier: p. 31.
  • Failure analysis of the BOP: p. 34.
  • Establishing and maintaining effective barriers: p. 47.
  • BOP not treated as a safety-critical element: p. 62.
  • Regulatory gaps: p. 93.
  • Recommendations: p. 95.

Source: U.S. government work, publicly released.

Sources

SourceLink
U.S. Chemical Safety Board, official copyRead ↗
U.S. Chemical Safety Board, investigation pageRead ↗

Part of the Deepwater Horizon (2010) investigation.

Note: External links, including Wayback Machine archives, take you off this site. Use your browser’s Back button to return to this post.