Addendum to the Forensic Examination of the Deepwater Horizon Blowout Preventer (DNV for BOEMRE, 2011)

November 25, 2026 · 8:11 AM PT

#deepwaterhorizon#macondo#blowoutpreventer#dnv#forensicengineering

DNV's follow-up to its BOP report: corrections, a fault tree for the off-centre drill pipe, alternative theories and further support for elastic buckling.

Note: External links, including Wayback Machine archives, take you off this site. Use your browser’s Back button to return to this post.

Det Norske Veritas (DNV), for the Bureau of Ocean Energy Management, Regulation and Enforcement, 30 April 2011.

Overview

A short addendum to DNV's March 2011 report. It corrects parts of the text and answers clarifications BOEMRE asked for: a fault tree for how the drill pipe ended up off centre, the alternative theories DNV considered, whether the upper variable-bore ram hoses were cut by an ROV, and further modelling in support of the elastic buckling theory.

Key pages

Printed page numbers, from the report's own table of contents.

  • Corrections to text: p. 2.
  • Fault tree analysis: p. 5.
  • Alternative theories: p. 8.
  • Cutting (or not) of upper VBR hoses via ROV: p. 10.
  • Support for the elastic buckling theory: p. 10.

Source: prepared by DNV under contract to BOEMRE and released publicly by the U.S. government.

Sources

SourceLink
BSEE, official copyRead ↗

Part of the Deepwater Horizon (2010) investigation.

Note: External links, including Wayback Machine archives, take you off this site. Use your browser’s Back button to return to this post.